|
Advertisement
|
|
|
|
Posted November 27, 2006
DNR ruling on nearby oil pipeline expected this week
By Andrew Hellpap
For the Marshfield News-Herald
State
Department of Natural Resources officials are expected to rule early
this week on a proposed petroleum pipeline from Superior to Delavan.
Phase
one of Enbridge Inc.'s 321-mile pipeline would cross through the
northeast corner of Clark County and diagonally from the northwest
corner to the southeast corner of Wood County, intersecting lakes,
rivers, forests and wetlands on private and public lands.
The
public comment period on a series of DNR permits for construction of
the pipeline has ended. About 30 individuals and several environmental
groups raised questions about the permits and the environmental impact
of the pipeline, said Jeff Schimpff, project manager for the DNR Office
of Energy in Madison.
"A lot of people are asking for environmental impact statements," he said. Of
particular interest to groups such as the River Alliance of Wisconsin
is the impact the construction would have on wetlands and forests,
according to a River Alliance news release.
"Wildlife
habitat will be cleared and outdoor recreation areas used for hunting
and fishing will suffer," said Lori Grant, policy manager for the
Alliance in the written statement.
The
biggest concern the DNR has discovered in reviewing public comments,
Schimpff said, is over the width of the 100-foot-wide construction work
space in wetlands and wooded areas.
"They have expressed a reserved interest in that," he said.
The pipeline would cross about 250 to 400 wetlands, Schimpff said.
The
weight of the 59-inch diameter pipe could be particularly damaging to
streams during spring spawning, he said. The pipe could change stream
beds, limiting the ability of fish to swim to their desired spawning
locations.
"That's a big pipe, so it's going to displace a lot of soil," Schimpff said.
Enbridge
is waiting for several permit approvals, including wetland water
quality certification, a storm water permit, pollution discharge and
permits to construct near American Indian burial grounds and sacred
sites, among others.
The
company does not foresee any problems securing the permits because
Enbridge has gone through two rounds of public comment on the pipeline
and has been working with the DNR to ensure the pipeline meets its
environmental protection requirements, said Denise Hamsher, Enbridge
director of regulatory and government affairs.
"I believe none of the restrictions are surprises," she said. "Work of this magnitude always requires some flexibility."
Enbridge officials want work started before winter to reduce the impact on the environment, Hamsher said.
If
everything goes according to Enbridge's design, 70 miles of the
pipeline would be installed in Washburn and Douglas counties this
winter, and the remaining section -- through central Wisconsin to
Delavan -- would be in place in the spring or summer, she said.
"We are all ready to go," Hamsher said.
The
U.S. portion of the pipeline expansion would add a total capacity of
400,000 barrels per day, at an estimated cost of about $1 million,
according to Enbridge's Web site.
|